Start with how you actually cook
Before any layout is drawn, write down how the room is used. Who cooks, how often, whether two people are in there at once, where shopping lands, where bins go, whether the room doubles as homework space. A layout that suits a household that eats out five nights a week is a poor layout for one that bakes at the weekend.
This sounds obvious, but most kitchen regrets are layout regrets, not finish regrets. Nobody complains about a handle. They complain that the dishwasher door blocks the oven, or that the only worktop run is on the far side of the room from the hob.
Survey and measure before you commit
A proper survey records wall deviation, floor level, ceiling height at several points, window reveals, existing service positions, joist direction and access route. In Victorian and Edwardian London stock, almost nothing is square, and a twenty-five millimetre fall across a five-metre run is common.
Those measurements drive real decisions: whether a tall run will actually stand up under a sloping ceiling, whether an island can be serviced without lifting a whole floor, whether the worktop can arrive in one piece up the stairs.
Lock the specification before making starts
Once cabinetry is cut, changes are expensive. Appliance models must be confirmed, because integrated units vary in width, hinge side and required clearances. Sink and tap choices affect worktop cut-outs. Extraction affects ceiling and cabinet design.
Sign off drawings that show elevations, not just a plan. Elevations are where you notice that the wall cabinet lands awkwardly against the window architrave, or that the plinth detail fights the existing skirting.
The right order of trades
Getting the sequence wrong is what causes delay and rework. The order below works for most refits and should be agreed with everyone before the first tool arrives.
- Strip out and dispose, including old units, tiling and flooring.
- Structural work: openings, steels, any wall removal, plus building control sign-off where needed.
- First fix plumbing and electrics to the agreed positions marked from the joinery drawings.
- Plaster, then allow drying time before anything is fixed to it.
- Flooring, if it runs under the units; otherwise after installation.
- Cabinetry installation, levelled and scribed.
- Worktop templating, then fabrication, then fitting - typically one to two weeks between template and fit for stone.
- Second fix plumbing and electrics, appliance connection and testing.
- Splashbacks, tiling and decoration.
- Snagging, adjustment of doors and drawers, final clean.
Realistic timescales
For a straightforward replacement in an existing layout, expect three to five weeks on site. Add structural work or a relocated kitchen and it becomes eight to twelve weeks. Bespoke cabinetry is made while site work proceeds, so the lead time usually overlaps rather than adds - provided the design was signed off early.
The two dates that matter are the drawing sign-off date and the worktop template date. Slip either and everything downstream moves, because stone fabrication and appliance deliveries are booked slots, not flexible ones.
Living through it
Set up a temporary kitchen somewhere else in the house with a kettle, microwave, fridge and a sink you can reach. Agree working hours, dust protection, where waste will be stored and which route through the house the trades will use. In flats, check the building's rules on working hours, lift protection and skip permits before you start.
Agree in writing who is coordinating. On smaller projects that is often the homeowner, and that is fine, as long as everyone knows it and someone is answering the questions that arise daily on site.
Snagging properly
Walk the room in daylight with the drawings in hand. Check that doors and drawers align and close evenly, that scribes are tight, that the worktop has no rough arrises, that appliance doors clear handles, that sockets are where they were specified and that lighting is switched as agreed.
Expect a small snag list; every project has one. What matters is that it is written down, dated, agreed and cleared in one visit rather than dribbling out over months.
Common mistakes worth avoiding
Choosing appliances after cabinetry, ordering stone before cabinets are level, running the extraction as an afterthought, forgetting a socket for the thing you use every morning, and specifying an island too narrow to walk around with an oven door open. All of these are cheap to solve on paper and expensive to solve on site.
The last one is worth a tape measure moment: a comfortable circulation gap either side of an island is around one metre, and 1.2 metres if two people work in the space at once.
Frequently asked questions
- Do I need planning permission for a kitchen renovation?
- Not usually for a like-for-like refit, but you may need building control approval for structural openings, new drainage or significant electrical work, and listed building consent for any works to a listed property.
- When should I order the joinery?
- As soon as drawings are signed off and appliances are confirmed. Typical workshop lead times run six to ten weeks, so ordering late is the most common cause of a stalled site.
- Can I keep my existing worktop?
- Sometimes, if the new cabinet layout matches the old cut-outs exactly. Stone rarely survives being lifted, so plan on the basis that it will not.